The details
In the school holidays, we were able to undertake demolition of existing narrow doors and installation of aluminium doors to minimise disruption during school term time. The works were spread around the entire school with lots of separate work areas and largely completed during term time which meant that effective safety procedures were required at all times. As work was completed around the school completed ramps and decks were handed over partially for school to use to ease the disruption to them.
This project was run concurrently with similar works at Rodney College next door by the same site team. The project, once on site, was run smoothly by our site team. The school experienced little disruption and are happy.