The details
The Project involved the construction of the following:
- Food Processing, Cooking & Packaging Line 1275m2
- Production Development Kitchen & Offices 600m2
- New Plantroom 88m2
- The project was successfully completed on time with all parties working well together to ensure a successful result for the Client
- Q compiled with the clients strict & rigorous Health & Safety requirements at all times
- Compliance with quality standards – yes
- Compliance with environmental standards – yes
- Completed by due date for completion – yes
- Final contract price as a percentage of contract price – less than 5%
- Any claims or disputes – n/a
- Working in a live environment whilst allowing the Client to continue to carry out their day to day business activities.