How we made a difference
Minimised potential delays due to unexpected geotechnical conditions and inclement weather by reviewing the works programme and rescheduling the construction team’s tasks.
Identified potential issues with fire rating design details for the individually titled units, and worked closely with the consultant to resolve these
The details
These architect-designed units were constructed with reinforced concrete foundations and slab, a structural steel frame and precast concrete wall panels.
A longrun roof was installed along with aluminium window joinery and electric roller doors, and a combination of facade panels and aluminium composite cladding for timber-framed exterior walls.
We installed steel composite flooring systems as well as in situ concrete mezzanine floors and lined the timber framed internal walls with plasterboard before painting.
Q Construction closely managed the installation of all building services – including plumbing, electrical, HVAC and fire sprinklers – as well as all floor coverings.
Concrete footpaths, a carpark with space for more than 30 vehicles and low maintenance landscaped gardens completed this high-quality build.
Reinforced concrete foundations and slab, precast concrete wall panels, structural steel frame, Traydek and insitu concrete mezzanine floors, Colorsteel longrun roof, timber framed exterior gutters and exterior walls with Exotec and Aluminium composite cladding, Aluminium window joinery, roller doors, timber framed internal walls plasterboard lined and painted, floor coverings and all building services (plumbing, electrical, HVAC and Fire including sprinklers), concrete footpaths & carpark, landscaping.